    hi,

    i have the following to calculate working days between 2 dates, but i am not getting the right amount. i should be getting 11 instead of 12, because feb 16 2009 was a holiday. can someone please advise? here is my code:

    Code:
    <?php
    //The function returns the no. of business days between two dates and it skips the holidays
    function getWorkingDays($startDate,$endDate,$holidays){
        //The total number of days between the two dates. We compute the no. of seconds and divide it to 60*60*24
        //We add one to inlude both dates in the interval.
        $days = (strtotime($endDate) - strtotime($startDate)) / 86400 + 1;
    
        $no_full_weeks = floor($days / 7);
        $no_remaining_days = fmod($days, 7);
    
        //It will return 1 if it's Monday,.. ,7 for Sunday
        $the_first_day_of_week = date("N",strtotime($startDate));
        $the_last_day_of_week = date("N",strtotime($endDate));
    
        //---->The two can be equal in leap years when february has 29 days, the equal sign is added here
        //In the first case the whole interval is within a week, in the second case the interval falls in two weeks.
        if ($the_first_day_of_week <= $the_last_day_of_week){
            if ($the_first_day_of_week <= 6 && 6 <= $the_last_day_of_week) $no_remaining_days--;
            if ($the_first_day_of_week <= 7 && 7 <= $the_last_day_of_week) $no_remaining_days--;
        }
        else{
            if ($the_first_day_of_week <= 6) {
            //In the case when the interval falls in two weeks, there will be a Sunday for sure
                $no_remaining_days--;
            }
        }
    
        //The no. of business days is: (number of weeks between the two dates) * (5 working days) + the remainder
    //---->february in none leap years gave a remainder of 0 but still calculated weekends between first and last day, this is one way to fix it
       $workingDays = $no_full_weeks * 5;
        if ($no_remaining_days > 0 )
        {
          $workingDays += $no_remaining_days;
        }
    
        //We subtract the holidays
        foreach($holidays as $holiday){
            $time_stamp=strtotime($holiday);
            //If the holiday doesn't fall in weekend
            if (strtotime($startDate) <= $time_stamp && $time_stamp <= strtotime($endDate) && date("N",$time_stamp) != 6 && date("N",$time_stamp) != 7)
                $workingDays--;
        }
    
        return $workingDays;
    }
    
    
    
    
    $holidays=array("2008-12-25","2008-12-26","2009-02-16");
    
    echo getWorkingDays("2009-02-01","2009-02-17",$holidays)
    
    
    
    ?>

    thanks in advance,
    geebee
  • TheServant
    Recognized Expert Top Contributor
    • Feb 2008
    • 1168

    #2
    In line 6 you have $days = ... + 1?? Why is that "+ 1" there?