Hi everyone
I'm doing a project at work and I'm managing most of it fine apart from one section where I need to calculate a due date. The due date is 5 working days after the date entered. I have a query and I've used the Due Date:DateAdd("d ","5",[Date]) calculation which does work out 5 days but is including weekends - I've tried substituting the "d" days for "w" days but still no luck! Help! I think I need a table of holidays but this is way above my talents (I'm an administrator not a programmer)
Thanks in advance for your help
I'm doing a project at work and I'm managing most of it fine apart from one section where I need to calculate a due date. The due date is 5 working days after the date entered. I have a query and I've used the Due Date:DateAdd("d ","5",[Date]) calculation which does work out 5 days but is including weekends - I've tried substituting the "d" days for "w" days but still no luck! Help! I think I need a table of holidays but this is way above my talents (I'm an administrator not a programmer)
Thanks in advance for your help