I had no experience in VB before writing this so bare with me...
the function below seems to work for certain cases, but not all (in some cases it is a week behind). Can anybody help me figure this out? It is supposed to take an integer(numDays ) and a date and calculate the date that is "numDays" weekdays from the start date. I don't know if it is the if statement at the bottom or the particular cases that seem not to work.
Here it is it seems to work for (days) cases 0, 3 and 4, but not for 1 or 2:
the function below seems to work for certain cases, but not all (in some cases it is a week behind). Can anybody help me figure this out? It is supposed to take an integer(numDays ) and a date and calculate the date that is "numDays" weekdays from the start date. I don't know if it is the if statement at the bottom or the particular cases that seem not to work.
Here it is it seems to work for (days) cases 0, 3 and 4, but not for 1 or 2:
Code:
' Accepts a start date and an integer(numDays) and calculates the date that is "numDays"
' number of work(week) days after the start date.
Public Function Workdays(ByRef startDate As Date, ByRef numDays As Integer) As Date
Dim weekHold As Integer
Dim dateHold As Date
Dim dayHold As Integer
Dim days As Integer
days = numDays Mod 5
dayHold = days
' if due date will fall on a sunday, advance two days.
Select Case days
' when you add 1 day and x weeks to the startDate to get the due date
Case 1
Select Case DatePart("w", startDate) + days
' sunday and monday
Case 1, 2
dayHold = days + 1
' saturday
Case 7
dayHold = days + 2
' else
Case Else
dayHold = days
End Select
' when you add 2 days and x weeks to the startDate to get the due date
Case 2
Select Case DatePart("w", startDate) + days
' sunday, monday and saturday
Case 1, 2, 7
dayHold = days + 2
' tuesday
Case 3
dayHold = days + 1
Case Else
dayHold = days
End Select
' when you add 3 days and x weeks to the startDate to get the due date
Case 3
Select Case DatePart("w", startDate) + days
' wednesday
Case 4
dayHold = days + 1
' Thursday and friday
Case 5, 6
dayHold = days
Case Else
dayHold = days + 2
End Select
' when you add 4 days and x weeks to the startDate to get the due date
Case 4
Select Case DatePart("w", startDate) + days
' wednesday
Case 4
dayHold = days + 1
' thursday and friday
Case 5, 6
dayHold = days
Case Else
dayHold = days + 2
End Select
' only case left is case where you just add a number of weeks to the startDate to get due date.
Case 0
dayHold = 7
End Select
'calculate due date
weekHold = numDays / 5
If weekHold > 0 Then
weekHold = weekHold - 1
End If
dateHold = DateAdd("ww", weekHold, startDate)
dateHold = DateAdd("d", dayHold, dateHold)
Workdays = dateHold
End Function